Meteor 4G Rollout
alt alt alt

 

Scope: Survey, Design and Deployment of 4G network

Client:LMI Ericsson and Meteor

Location: Republic of Ireland (Nationwide)

Date: July 2013 to August 2014

Requirements: The Obelisk Group were selected by LMI Ericsson to design and deploy 4G technology on existing Meteor sites (Rooftop, green field and co-locates) in the major cities and towns to ensure coverage was in place for Meteors 4G launch.

Solution: Obelisk was responsible for the end to end delivery of sites from survey through to design, installation, integration and call testing of the new 4G service. Our scope of work in this project included:

Obelisk Impact: In a very short ramp up period, Obelisk was able to mobilise multiple survey teams comprising of site designers, technical engineers and rigging resources to audit and design the best solution for each site. By mobilising multiple teams, Obelisk were able to ensure that there were sufficient sites designed and available to achieve a consistent build and integration rate for Meteor. This in turn ensured that Meteor could achieve its aggressive targets prior to the official 4G launch date. Obelisk delivered consistently on time and within budget to the highest quality and safety standards.

  • Programme & Project management
  • Technical site solution design
  • Appointed Project supervisor design stage and construction stage
  • All rigging works and identified H&S upgrades
  • Deployment and integration of new 4G hardware (Antennas & Remote Base Stations)
  • Site handover back into operations
  • Logistics and warehousing for the duration of the site builds

Obelisk Impact: In a very short ramp up period, Obelisk was able to mobilise multiple survey teams comprising of site designers, technical engineers and rigging resources to audit and design the best solution for each site. By mobilising multiple teams, Obelisk were able to ensure that there were sufficient sites designed and available to achieve a consistent build and integration rate for Meteor. This in turn ensured that Meteor could achieve its aggressive targets prior to the official 4G launch date. Obelisk delivered consistently on time and within budget to the highest quality and safety standards.