Glanaruddery Windfarm

<< Obelisk Power Systems Ltd. Services

Client:   Impax Asset Management
Location:   Kerry, Ireland
Value:   €650k

Electrical Balance of Plant contract for the Glanaruddery 11 X 3.3MW turbine windfarm. Glanaruddery is connected to the existing Cloughboola 110/20kV substation via 7km U/G 20kV cable.

Project Scope:
Design and Build contract for the engineering, procurement, construction and commissioning of electrical and civil works to all Impax, ESB Networks and Eirgrid functional specifications including;

  • 2 no. 20kV Siemens NxPlusC Switchboards

  • HV system control, protection, metering, remote annunciation panels and battery systems

  • 20kV collector circuit cabling

  • Fibre Optic network

  • Complete commissioning of substation and HV cable circuits including VLF testing